Relocation of 4 GE TM2500 Gas Turbines
Disassembly, transport, reassembly and commissioning of four GE TM2500 gas turbines and associated electrical infrastructure for Quaint Energy.
ClientQuaint Energy
LocationAfam, Rivers State, Ughelli, Delta State
UnitTM11, TM12, TM27 and TM28
Project Overview
Scope of Work
Disassembly, assembly and commissioning of TM11, 12, 27 and 28
Disassembly, assembly and commissioning of 2 GSUT (generator step-up transformers)
Disassembly, assembly and commissioning of 2 x 1667kVA transformers
Cable tray construction and cable laying
HV cable laying and bushing termination
Protection system functional testing and verification
Generator testing
Plant commissioning
On Site